CPST – LCWSC Water Tank

Hickory Tavern 250,000 Gallon Elevated Water Tank Replacement

Implementation Plan as of March 1, 2021

Cost Estimate:

  • $1,994,755

Funding Source:

  • Laurens County Capital Project Sales Tax

Project Update:

  • Geotechnical Exploration: COMPLETED
    • Preliminary results look good.
    • Report made available in 2 weeks
  • Preliminary survey: COMPLETED
  • 60% Designed by the end of March 2021
  • Expected construction to begin Summer 2021