CPST – Agricultural Center

Implementation Plan as of January 27, 2021

Project 4: Agricultural Center
Project Amt: $7,983,008
Entity: County Council
Cash Flow & Schedule: TBD – Estimated for now
A. Q2 21 Site Acquisition: $1,200,000
B. Q2-Q4 21: Design/Testing/Construction Acquisition: $150,000
C. Q1 22-Q4 23 Construction: $6,633,008

Action Plan
Step 1: Committee formed to advise County Council and guide the design and implementation process: COMPLETED January 26, 2021

Dr. John Irwin
Annette Bodie
Mason Addy
Jay Wham
Ellington Willis

Plans are a work in progress and are subject to change over time.